               Report  of Year 2000 Compliance Project                                                                                                                 
               THE BANGCHAK PETROLEUM PUBLIC COMPANY LIMITED                                   
Business: Energy                                                                                                                        
Head Office: 38 Srinakarin Road, Prawet, Bangkok 10260                                                                                                                  
Telephone: 301-2700  Facsimile: 301-2859                                                                                                                        
Report on the status of the Year 2000 Compliance Project, 
the sixth report (as of September 30, 1999).                                                            
Bangchaks Preparation for the Y2K Compliance: 
           Third Quarter 1999 Progress
I. Project Execution during the Last Quarter                                                                                                               
  Bangchak Master Plan for Year 2000 Compliance project 
has been divided nto five steps as follows :                                                      
       Step 1 : Overall Project Management                                              
       Step 2 : Risk Analysis and Impact Assessment / 
                Implementation and Validation Planning                                                          
       Step 3 : Implementation                                                          
       Step 4 : Validation                                                              
       Step 5 : Contingency Plan                                                        
  In the first quarter of 1999, Bangchak has completed 
the work step 1 to step 4. For the work step 5, 
the contigency plan has been completed in the third quarter                                                                                        
of 1999. It means the Year 2000 Compliance project of 
Bangchak is totally completed at 100% in the third quarter of 1999.                                                 
II.     Progression                                                                                                             
       As of  the Third Quarter of 1999, the project 
progression is 100% as shown below.                                                                           
                                                WEIGHTING, %  ACTUAL                          
                                           (OVERALL PLAN)    PROGRESS, %                              
    1.  Overall Project                         5               5                               
    2.  Risk Analysis and Impact Assessment     17              17                              
    3.  Implementation                          60              60                              
    4.  Validation                              12              12                              
    5.  Contingency Plan                        6               6                               
                                               100             100                                                   
III.    Situation Analysis and Management View                                                                                                          
   The project execution for the Year 2000 Compliance from 
the first quarter of 1997 till the end of third quarter of 1999 
has been satisfactorily completed as scheduled  include 
the contingency plan. The training of contingency plan has been 
continuously practised to ensure the readiness of company systems.      
                           YEAR  2000  COMPLIANCE  PROJECT                                                                                         
                                                   YEAR         1997            1998           1999                        
ACTION PLAN  FOR  COMPANY CRITICAL ITEMS           QUARTER  Q1  Q2  Q3  Q4  Q1  Q2  Q3  Q4  Q1  Q2  Q3  Q4
1. Overall Project Management                                                                                                                           
  - Establish Y2K committee/Assign managers and team members ***                                                                                                                       
  - Control plan and revise scheduling                        *********************************                                
2. Risk Analysis and Impact Assessment                                                                                                                          
  A.IT Group  - APPLICATION SOFTWARE / DATABASE                    **                                                                                              
              - NETWORK / OS / HARDWARE                             ******                                                                                         
  B. Non-IT Group                                                             **   ****                                                                                  
  C. Supply Chain                                                              ********                                                                        
3. Implementation                                                                                                                               
       A. IT Group     - APPLICATION SOFTWARE / DATABASE                                                                                                               
                       +  MARKETING & SALES                                ************                                                                           
                       +  ACCOUNTING / FINANCIAL              ******************************                                     
                       +  OIL RECORD                                       *******************                                                                          
                       +  HUMAN RESOURCE                                      ******************                                                                               
               - NETWORK / OS / HARDWARE                                       ********                                                                              
       B. Non-IT Group                                                           ***   ***                                                      
4. Validation                                                                                                                           
       A. IT Group     - APPLICATION SOFTWARE / DATABASE                                *******                                                                               
                       - NETWORK / OS / HARDWARE                               ****** ******                                                                                
       B. Non-IT Group                                                           ****   **                                                       
5. Contingency Plan                                                                                                                             
       A. IT Group                                                        **          *****************                                                             
       B. Non-IT Group (Refinery completed, Other systems in progress)    ******************                              
       C. Supply Chain                                                                  ***                                               
          ---- PLAN          **** ACTUAL
            Certificate of Correctness
  Report  of Year 2000 Compliance Project FORM 57 (Y2K)
     The Bangchak Petroleum Public Company Limited by Board of Directors 
(hereinafter called the Company) have examined the statement 
in the report concerning to this Y2K Compliance Project 
(hereinafter called the Project) and certify that all are 
completed, accurate, true, and do not make others misunderstand, 
or lack the information in significance that may damage 
to shareholders, or stock exchange investors
     To be the evidence, all documents which have been certified 
by the Company, we empowered Mrs Saisunee  Sangnimnuan 
(hereinafter called the Attorney) to have the authorized 
signature to sign in all documents concerning to the Project.  
All documents, without Attornys signature, shall not be 
deemed as a part hereof.
          Name                         Position             Signature
1 Mr. Somchai    Richupan               Chairman      
2 Mr. Chirayu    Isarangkun na-Ayuthaya Director        
3 Mr. Prasert    Bunsumpun              Director    
4 Mr. Piyasvasti Amranand               Director        
5 Mrs.Puntip     Surathin               Director        
6 Mr. Pichai     Chunhavajira           Director        
7 Mr. Wanchai    Thanittiraporn         Director        
8 Mr. Sirichai   Sakornratanakul        Director        
9 Mr. Sommai     Phasee                 Director        
10Mr. Anan       Nadtasomboon           Director        
                         Name                 Position      Signature
Attorney        Mrs. Saisunee   Sangnimnuan     Manager                            
                                                                                                                       
                                                                                                                       
                                                                                                                       
                                                                                                                       
                                                                                                                       
                                                                                                                       
                                                                                                                       
                                                                                                                       
                                                                                                                       
                                                                                                                       
                                                                                                                       
                                                                                                                       
                                                                                                                       
                                                                                                                       
                                                                                                                       
                                                                                                                       
                                                                                                                       
                                                                                                                       
                                                                                                                       
                                                                                                                       
                   